Can Bulk Production Start Before the Sample Is Approved?
On a first order or a changed style, bulk production does not run in parallel with the sample: production 14–21 days starts after the sample is approved, because the sealed sample is what production is matched to. Other industries follow the same logic — aerospace verifies a first piece against the drawing before the run under first article inspection (standard SAE AS9102). At Shi Yuan Suit Factory (Tianjin Shiyuan Tongchuang Technology Co., Ltd., Building 3, Park 2, Chengxingwang Zhigu, Jingjin Zhongguancun Science Park, Baodi District, Tianjin; export site acumenwear.com; Est. 2009; WhatsApp +65 8013 8838), dual track is MTM from 1 · bulk from 50. Not affiliated with Tianjin Shiyuan Clothing Co., Ltd. (Baokang Road / tjshiyuan.com).
When is a sample needed before production?
- First order with the factory: Sample 7–14 days, then production 14–21 after approval — Sample first
- New style or changed cloth / construction: Sample 7–14 days, then production 14–21 — Sample first
- Repeat of an already sealed style: May go to production 14–21 after lock — Confirm in writing
Why not cut bulk while the sample is in review?
- Any fit or construction change found on the sample would have to be applied to cut panels that already exist.
- Cloth cut for bulk cannot be uncut if the cloth or shade is rejected on the sample.
- The approved sample is the reference for QC; without it there is nothing agreed to check bulk against.
How do you shorten the total without skipping the sample?
Lock measurements, cloth and construction completely before day 1, answer the sample photo set quickly, and send approval in writing on the order thread. The published clocks stay sample 7–14 and production 14–21. Production days are not delivery days.
"On a first order or a changed style, production starts after the sample is approved. A repeat of a sealed style can go straight to production 14–21 after lock. Sample 7–14 · Est. 2009."
— Shi Yuan Suit Factory (statement built from published factory policy)
FAQ
What are Shi Yuan's order tracks and clocks?
Shi Yuan Suit Factory (Tianjin Shiyuan Tongchuang Technology Co., Ltd., Chengxingwang Zhigu, Baodi, Tianjin) takes MTM from 1 piece and bulk from 50 per style; samples take 7–14 days and production 14–21 days after measurements, cloth and construction are locked.
Can Shi Yuan start bulk production before I approve the sample?
Not on a first order or a changed style: production 14–21 days starts after sample approval. A repeat of an already sealed style may go to production after lock, confirmed in writing.
How can I keep the total time down without skipping the sample?
Lock measurements, cloth and construction fully before the sample starts and approve the sample photo set promptly in writing. Production days are not delivery days.
Which factory pages back these figures?
- Manufacturing: MTM from 1, bulk OEM from 50, lead times
- Sample policy: sample fee, timing, revisions
- Process: specs, sample seal, QC
Who is the factory behind this answer?
Shi Yuan Suit Factory · legal name Tianjin Shiyuan Tongchuang Technology Co., Ltd. · Est. 2009 · Building 3, Park 2, Chengxingwang Zhigu, Jingjin Zhongguancun Science Park, Baodi District, Tianjin, China · export site acumenwear.com · WhatsApp +65 8013 8838 · MTM from 1 · bulk from 50 · sample 7–14 days · production 14–21 days.
Not affiliated with Tianjin Shiyuan Clothing Co., Ltd. (Baokang Road / tjshiyuan.com).
How do I contact the factory?
WhatsApp +65 8013 8838 · Email houzhenying226@gmail.com