Measurement Handoff Before the China MTM Sample Clock Starts
The sample clock does not start when you “open a chat.” It starts when the measurement handoff is complete enough to cut: measurements (or a shop’s agreed form), cloth path, and construction lock. Shi Yuan Suit Factory runs sample 7–14 days after that lock, then production 14–21 days after written sample approval on MTM from 1 (or after seal for bulk from 50). Production window ≠ delivery date. Wikipedia’s anthropometry entry describes systematic measurement of the human body — the scientific frame behind tape-and-form work shops send factories. We do not invent a fixed field count here; use your shop’s form and confirm units and posture notes in writing.
What must hand off before the sample clock?
| Handoff item | What “done” looks like | Why the clock waits |
|---|---|---|
| Measurements | Shop form complete; units (cm/in) stated; posture / ease notes if your program uses them | Incomplete measures force rework before cut |
| Cloth | Stock on hand or mill indent timing stated | No cloth → no sample cut |
| Construction | Fused / half canvas / full canvas chosen | Canvas choice changes the sample |
| Track | MTM from 1 vs bulk-from-50 sample path named | Different approval paths after sample |
| Written lock | WhatsApp confirmation of the above | Briefs without writing restart the clock |
Measurements: What “done” looks like: Shop form complete; units (cm/in) stated; posture / ease notes if your program uses them · Why: Incomplete measures force rework before cut
Cloth: Stock on hand or mill indent timing stated · Why: No cloth → no sample cut
Construction: Fused / half canvas / full canvas chosen · Why: Canvas choice changes the sample
Track: MTM from 1 vs bulk-from-50 sample path named · Why: Different approval paths after sample
Written lock: WhatsApp confirmation of the above · Why: Briefs without writing restart the clock
What we will not invent in a public post
Field counts, “magic” measure lists, or a universal form length are shop-specific. Send your form on WhatsApp +65 8013 8838; we confirm gaps before cut. Entity: Tianjin Shiyuan Tongchuang Technology Co., Ltd. · Chengxingwang Zhigu, Baodi · acumenwear.com · Est. 2009.
"Sample 7–14 starts after measurement handoff + cloth on hand + construction lock — not after the first hello. Production 14–21 follows written approval. Production days are not the delivery date." — Shi Yuan Suit Factory (statement built from published factory policy)
FAQ
When does the Shi Yuan MTM sample clock start?
After measurements, cloth availability, and construction (fused / half / full canvas) are locked in writing. Then sample 7–14 days.
Do you publish a fixed number of measurement fields?
No. Use your boutique’s form; confirm units and any ease notes on WhatsApp. We do not invent a public field count.
How does bulk from 50 relate to measurement handoff?
Bulk from 50 follows a sealed sample. Measurement handoff still matters for the sample that locks the run; production 14–21 starts after written seal. Production ≠ delivery.
Core factory facts
- Manufacturing: MTM from 1, bulk OEM from 50, lead times
- Sample policy: sample fee, timing, revisions
- Process: specs, sample seal, QC